Indah Water Konsortium Sdn Bhd - Butterworth Selatan
Runner-Up
Energy Management in Small & Medium Industry
Project Name: Energy Management at Butterworth-South Regional Sewage Treatment Plant
IWK Butterworth is a mechanized plant with capacity to treat sewage meeting the Department of Environment`s effluent quality discharge of Standard B.
The annual energy savings for IWK Burtterworth in year 2022 is 961,305 kWh that is equivalent to RM 226,373 with the carbon emissions of 562 tonne They installed the Solar PV which contributed the energy saving of 293,233 kWh equals to RM 19,138.